Lawson Turnback, NSW - Stage 2a OHW Complete

On the weekend of 29‐30 May, 2010 a team of 30 completed Stage 2a construction of the overhead wiring. The team worked through adverse weather conditions including rain and wind to achieve the outcome.

Stage 2b of the overhead wiring is expected to take place 7‐8 August, 2010.